Talisker updates 2026 operations
TORONTO, Sept. 14, 2026 (GLOBE NEWSWIRE) -- Talisker Resources Ltd. ("Talisker" or the "Company") (TSX: TSK, OTCQB: TSKFF) is pleased to provide an operational update on activities at its Bralorne Gold Project in British Columbia.
Key Highlights
Gold Production and Sales: Produced approximately 4,884 ounces of gold from 19,014 tonnes mined at an average grade of 7.99 g/t Au up to August 31, 2026. Sold 18,499 tonnes at an average grade of 8.05 g/t Au, representing 4,788 contained gold ounces. In addition, 770 ounces was sold as gold concentrate for a total of 5,558 ounces.
Ore Inventory: Current inventory of approximately 8,100 tonnes, supporting continued marine shipment schedules through the remainder of 2026.
Underground Development: Completed 2,265 metres of underground development year-to-date, comprising 1,041 metres of operating development and 1,224 metres of capital development.
Mustang Production and Growth: Successfully mined the Alhambra vein stopes in the upper Mustang and added new stopes to the mine plan following positive drilling results that extended the Alhambra vein. Production long-hole drilling is underway on the BK-9870 vein system, with stoping scheduled to begin by late Q3 2026.
Lower Mustang Development: Advanced the Lower Mustang Decline by 329 metres in 2026, opening access to the 1045, 1030 and 1015 levels, supporting development of 13 new mineralized headings, with five currently producing and multiple additional headings planned following positive BK and Alhambra vein intercept drill results.
Bralorne West Development: Completed 108 metres of capital development on the Bralorne West Decline in 2025 and 296 metres in 2026 for a total of 404 metres. Constructed a resource definition drill bay at the bottom of the ramp, and commenced Phase 3 lateral development on September 3, 2026, to advance towards the centre of the Bralorne West Zone.
Key Underground Infrastructure: Installed